Findlay Industrial Park – Phase 3

Findlay Industrial Park – Phase 3

LSSE prepared Property and Subdivision plans on this 373-acre former surface mine property for the purpose of constructing a 1,200 LF extension of Solar Drive in preparation for future site development.

Work included preparation of site development plans, including grading, drainage, and utilities; street lighting plans; sanitary sewers and waterlines; erosion and sedimentation control plans, report and details; stormwater management report; post-construction stormwater management report; and roadway design. 

LSSE’s scope of work included:

  • Conceptual Plan Preparation
  • Surveys for Wetland Location and Subdivision Plans / Construction Stakeout
  • Subdivision Plan Preparation
  • Erosion and Sedimentation Control Plan and Report
  • Utility Coordination
  • Preliminary and Final Land Development Plans
  • Stormwater Management Plan and Report, including green infrastructure BMPs
  • DEP Permitting (NPDES) and Post Construction Stormwater Management including design of vegetated swales, a bio-filtration fore bay, and stormwater dry detention basin
  • Construction Specifications
  • Contract Administration

MARKETS:

  • Industrial

SERVICES:

  • Civil-Site Engineering
  • Landscape Architecture and Planning
  • Surveying